Botley Road, Southampton

Paul Basham Associates provided post-permission civil engineering support to Ibex Homes, incorporating Section 38 Highway Design and Implementation as well as a Section 104 Drainage Agreement.

The brief

Following a successful application for nine properties, Ibex approached Paul Basham Associates to assist with the detailed internal design to allow for the occupation of the development and dedication of the highway.

Our civils team were also required to undertake drainage design and facilitate the Section 104 Agreement.

Our approach

We undertook pre-submission dialogue with Southern Water to agree the principles of the S104 submission, followed by a design package. This was completed in tandem with the Section 38 design package, securing design approval for both aspects of the construction process.

The result

Our civil team successfully secured Section 38 and 104 approvals and provided site-support whilst the highway works were undertaken.